How to Review a Construction Draw Request, Line by Line

Rate snapshot

Fed funds target3.75% to 4.00%Last changed Sept. 17, 2026
SOFR3.88%Oct. 7, 2026, down 2 bp from Oct. 6
1-year Treasury4.42%Oct. 7, 2026 close, down 4 bp
30-year Treasury5.67%Oct. 7, 2026 close, up 3 bp
Freddie Mac 30-year fixed7.28%Survey week of Oct. 1, 2026
Single-family starts918,000August 2026 SAAR, up 7.6% from July

The curve steepened yesterday. SOFR came in two basis points lower at 3.88%, the one-year fell four basis points to 4.42%, and the thirty-year went the other way, up three to 5.67%. Freddie Mac posts this week’s mortgage survey later this morning, which for anyone building for-sale product is the number that decides whether the buyer at the end of the project can close.

If you are building, both ends of that curve are in your deal. Your construction loan floats over SOFR, so the front end sets your carry. Your sellout depends on the thirty-year fixed at 7.28%, so the long end sets your absorption. In between sits the thing that actually determines whether the loan finishes: the draw package your general contractor submits every month, and whether anyone reads it closely.

We took a real-shaped draw package on a 24-unit townhome community and ran the three tests a lender should run on it. The draw was arithmetically correct. It also left the loan with $60,243 more cash in the ground than there was work in the ground, and committed the entire $429,300 retainage balance to covering the gap. The draw passed the test most sponsors run and failed the two that matter.

The project

Twenty-four for-sale townhomes in Central Florida, month nine of a seventeen-month schedule, draw seven under review. Single-family starts ran at a 918,000 annual rate in August, up 7.6% from July, so this is not a market where a stalled project gets rescued by absorption. The budget:

LineAmountShare
Land$1,450,00012.9%
Site work and horizontal$1,180,00010.5%
Vertical hard costs$6,005,00053.2%
General conditions and fee$545,6004.8%
Soft costs$1,120,0009.9%
Contingency$420,0003.7%
Interest reserve$560,0005.0%
Total project cost$11,280,600100.0%
Loan at 70% of cost$7,896,420
Sponsor equity$3,384,180
Hard construction contract$7,730,60068.5%
All-in cost per unit$470,025
Loan rate7.38%SOFR + 350 bp

Your 10% retainage is 6.85%

Start with the number everyone trusts. The loan agreement says 10% retainage, which sounds like a tenth of the project held back until the work is done. It is not, because retainage is withheld on the hard construction contract and nothing else. Land, soft costs, contingency, and the interest reserve are advanced in full.

Retainage structureHeld at completionAs % of total cost
10% on hard construction$773,0606.85%
10% on hard construction, excluding GC fee$718,5006.37%
10% stepping to 5% after 50% complete$579,7955.14%
10% on every budget line$1,128,06010.00%

The structure in this loan withholds 6.85% of the project. If the contract carves the general conditions and fee out of retainage, which many do because the GC asks and it sounds reasonable, it drops to 6.37%. A step-down to 5% past the halfway mark, a very common concession, takes it to 5.14%. That is half of what the term sheet appears to promise.

Draw 7 as submitted

Here is the continuation sheet. Scheduled value, previously billed, this period, stored materials, total completed and stored, percent, and balance to finish. These are the columns on the standard AIA continuation sheet, and they are the only numbers most reviewers look at.

LineScheduledPreviousThis drawStoredTotal C+S%Balance
General conditions$545,600$330,000$48,000$0$378,00069%$167,600
Site work and utilities$1,180,000$985,000$62,000$0$1,047,00089%$133,000
Foundations and slabs$742,000$668,000$44,000$0$712,00096%$30,000
Framing and trusses$1,505,000$742,000$268,000$0$1,010,00067%$495,000
Roofing$486,000$97,000$118,000$0$215,00044%$271,000
Windows and exterior doors$372,000$0$26,000$214,000$240,00065%$132,000
Plumbing rough$418,000$188,000$71,000$0$259,00062%$159,000
Electrical rough$396,000$142,000$83,000$0$225,00057%$171,000
HVAC rough$354,000$106,000$67,000$0$173,00049%$181,000
Stucco and exterior finish$642,000$0$34,000$0$34,0005%$608,000
Interior finishes$725,000$0$0$0$00%$725,000
Landscape and hardscape$365,000$0$0$0$00%$365,000
Totals$7,730,600$3,258,000$821,000$214,000$4,293,00055.5%$3,437,600

The request is $1,035,000 gross, less $103,500 of retainage, for a net advance of $931,500. The arithmetic is right. Every line foots, the percentages match the values, and the balance to finish reconciles to the contract. A reviewer checking the math signs this.

Three tests, three answers

Percent complete is one test. There are two others, and on this draw they disagree with the first by a material amount.

TestCompleteValue supported
1. Percent complete as submitted, including stored materials55.53%$4,293,000
2. In-place work only, stored materials stripped out52.76%$4,079,000
3. Third-party inspector, assessed line by line49.20%$3,803,457

Two line items account for nearly the whole gap. The first is $214,000 of windows and exterior doors sitting on site, uninstalled, billed at full value. Stored materials can be legitimate, but they are inventory, not improvement, and inventory walks off job sites.

The second is general conditions, billed at $378,000 of $545,600, or 69.3%, on a project that is in month nine of seventeen, which is 52.9% of the schedule. General conditions are a time-based cost, supervision, trailers, dumpsters, temporary power, so time elapsed is the right measure. Billed on that basis the line supports $288,847, meaning it is front-loaded by $89,153.

Front-loading general conditions is the oldest move in draw management, and it is not necessarily dishonest. A GC who mobilized heavily and carried three supervisors through the framing push has a real argument. But the effect on the lender is identical either way: cash leaves the loan ahead of the work, and if the GC walks in month twelve, the money spent on month-fifteen supervision is gone.

The number that matters

Forget percentages for a moment and ask the only question that survives a default: how much cash has the loan put out, and how much work is standing on the site?

Position after draw 7Amount
Cumulative billed, total completed and stored$4,293,000
Less cumulative retainage held$429,300
Cash actually advanced against hard costs$3,863,700
Value of work in place per the inspector$3,803,457
Cash advanced in excess of work in place$60,243

The loan is $60,243 past the work. That is a small number against an $11.3 million project, and that is exactly why it gets missed. The significant part is what it says about the retainage: the gap between billed value and real value is $489,543, and retainage held is $429,300. Retainage absorbed the gap and ran out.

Put differently, covering this draw’s over-advance would have required a retainage rate of 11.40%, not 10%. The protection in the loan agreement was calibrated to a job where the billing is honest within a tenth. This one is off by an eighth, and the cushion is gone in month nine of seventeen.

Why draw 7 is the thin spot

Retainage is usually described as a cushion against the cost to finish. Compare the two directly across the life of the job and the description falls apart.

CompleteRetainage heldBalance to finishRetainage as % of balance
20%$154,612$6,184,4802.5%
38%$293,763$4,792,9726.1%
49%$379,495$3,935,6489.6%
65%$502,489$2,705,71018.6%
81%$626,179$1,468,81442.6%
88%$680,293$927,67273.3%
91%$703,485$695,754101.1%
94%$726,676$463,836156.7%

Retainage does not exceed the balance to finish until the job is about 91% complete. For the first nine-tenths of the project, the money held back is worth less than the work remaining, often far less. At the halfway mark it covers under a tenth of what is left to build.

This is not an argument for higher retainage. It is an argument that retainage was never the control. The control is the draw review, because retainage only becomes meaningful at the point in the schedule where almost nothing can go wrong anyway.

What the correction costs

Two adjustments fix this draw. Hold the stored materials until they are installed, and reduce general conditions to time elapsed.

ItemAmount
Draw as submitted, gross$1,035,000
Hold stored materials pending installation-$214,000
General conditions reduced to time elapsed-$48,000
Corrected gross draw$773,000
Less 10% retainage-$77,300
Net funded$695,700
Reduction from the request$262,000
One month of interest on the amount not advanced$1,611

The reduction is 25% of the request, and the cost of the delay to the borrower is $1,611 of interest for one month. That asymmetry is the practical case for reading the package. A careful review costs the deal a rounding error and protects a quarter of a million dollars of advance.

There is a harder conversation underneath it. If the inspector is right, the true cost to complete is $3,927,143 rather than the $3,437,600 the draw implies, a $489,543 difference. That consumes 117% of the $420,000 contingency, which means the contingency is already gone in month nine and any further overrun is unfunded. Better to find that in month nine than at the final draw.

Simplifications: this is a constructed example, not a specific deal, and interest is computed 30/360 at the closing rate on the amount not advanced. General conditions assessed on straight time elapsed, which overstates the adjustment where a GC genuinely front-loaded supervision and understates it where mobilization is still ahead. The inspector percentages are assumed, and in practice a line-by-line assessment carries its own error band. Excluded: change orders pending at the time of the draw, soft-cost draws, the interest reserve draw, sales and marketing timing, and any horizontal release or partial lien release mechanics tied to unit closings.

Three Florida lien waiver rules sponsors get wrong

The waivers in the draw package are the other half of the review, and Florida’s lien statute has specific requirements that routinely get papered over.

  1. An advance waiver is worthless. Florida Statutes section 713.20(2) says a right to claim a lien may not be waived in advance, and any such waiver is unenforceable. A waiver signed at contract execution covering future work protects nobody. Lien rights can only be waived as to labor, services, or materials already furnished.
  2. You cannot demand your own form. Section 713.20(6) provides that a person may not require a lienor to furnish a waiver in a form other than the statutory forms. Lenders and sponsors who insist on a custom waiver are asking for something the statute does not permit, and a non-conforming waiver is then enforceable only on its own terms under 713.20(8).
  3. A waiver can be conditioned on the check clearing. Under 713.20(7) a lienor who signs a waiver in exchange for a check may condition it on payment of that check. So an unconditional waiver collected before funds clear is not the clean release it appears to be, which is the whole reason the conditional and unconditional distinction exists in a draw package.

The line-by-line checklist

  1. Foot the continuation sheet against the contract sum and against the last approved draw. A line whose scheduled value moved without an executed change order is the single most common error in a draw package.
  2. Recompute every percent complete from the values rather than reading the percentage column. The column is typed by hand.
  3. Pull stored materials out and test the percentage again. Then confirm the materials are on site, insured, segregated, and that title has passed.
  4. Test general conditions against time elapsed, not against percent complete. Flag any line billed more than five points ahead of schedule.
  5. Compare the balance to finish on each line against the cost to actually finish it. These are the same number only if the budget is still right.
  6. Reconcile cash advanced to date against the inspector’s assessed value in place. This is the one test that tells you your actual collateral position.
  7. Check that conditional waivers cover the current draw and unconditional waivers cover the prior one, and that the sub list matches the lien law notices on file.
  8. Confirm the inspector walked the site for this draw rather than updating a prior report, and that the date on the report precedes funding.
  9. Re-forecast remaining contingency after every adjustment. Contingency is the only line that tells you whether the project is still fundable.
  10. Verify that retainage held equals the retainage percentage applied to cumulative billings, including on prior draws. Arithmetic drift here is common and always in one direction.

Red flags

  1. Stored materials appearing on a line that has never been billed for installed work.
  2. General conditions tracking ahead of every other line, draw after draw.
  3. A draw where the percent complete rose but the inspector’s assessed value did not.
  4. Scheduled values shifting between lines with the contract sum unchanged, which is a change order that nobody executed.
  5. Lien waivers signed by someone other than the party that furnished the work, or dated after the funding request.
  6. A GC requesting a retainage step-down at the same draw the schedule first slips.
  7. Contingency drawn to cover a line that was simply underbid rather than an actual unforeseen condition.

How QuadBlock can help

We finance ground-up SFR and townhome communities alongside bridge and transitional loans from $250,000 to $30 million, and we have closed more than 30 deals across every state except Oregon and Nevada. We review draws against the inspector’s assessed value and the cost to complete, not just the percentage on the continuation sheet, because catching a $262,000 over-advance in month nine is worth more to a sponsor than approving it quickly. Send your budget, schedule of values, and GC contract to us at quadblockcapital.com and we will walk the draw mechanics with you before the first request.

This article is for general educational purposes and is not tax, legal, or investment advice. The project shown is a hypothetical model built from the market data cited below, and the budget, rate, and leverage inputs are illustrative rather than quoted terms. The discussion of Florida Statutes chapter 713 is a general summary of statutory text and not legal advice; lien and waiver requirements vary by state and by the facts of each project, and you should consult construction counsel licensed in your jurisdiction. Loan structures, draw procedures, and underwriting standards vary by lender, asset, sponsor, and market, and actual results will differ.

Sources

  1. Federal Reserve Bank of New York, Secured Overnight Financing Rate, observations through Oct. 7, 2026
  2. U.S. Department of the Treasury, Daily Treasury Par Yield Curve Rates, October 2026
  3. Board of Governors of the Federal Reserve System, Open Market Operations, federal funds target range history
  4. Freddie Mac, Primary Mortgage Market Survey, week of Oct. 1, 2026
  5. U.S. Census Bureau and HUD, New Residential Construction, August 2026